Environmental review and permitting timeline

This graphic timeline outlines how the permitting process and environmental review process progress simultaneously.

Environmental review and permitting timeline
Timeline

Environmental review

Determine if environmental review is needed

Permitting

Determine required permits and certifications

Environmental review

Environmental Assessment Worksheet (EAW)

Proposers submit an EAW to MPCA

Permitting

Submit permit applications

Permit applications can be submitted concurrently with an EAW, but they will not be issued until ER process is complete

Environmental review and permitting

Outreach to Tribal Nations

Environmental review

MPCA publishes EAW

Permitting

Consult with state agencies

Projects often require permits from multiple agencies

Environmental review

EAW public comment period

The public can review and provide feedback

Permitting

Permit public comment period

Proposal is open to community feedback

Environmental review

Decision on environmental impact statement (EIS)

MPCA determines if an EIS is needed

Permitting

Issue final permits

Project can be started if an EIS is not needed