Cottonwood River - Turbidity: TMDL Project

Minnesota's Impaired Waters and TMDLs

The Cottonwood River watershed area covers 840,192 acres (1,313 square miles) of land and is located in parts of Brown, Cottonwood, Lyon, Murray, and Redwood Counties. The Cottonwood River originates near Balaton in southwest Lyon County, Minnesota, and flows about 150 miles east to the Minnesota River near New Ulm. The dominant land use in the watershed is cultivated agricultural row crops, accounting for 88% of all land use. The Redwood-Cottonwood Rivers Control Area (RCRCA) is responsible for the completion of the TMDL assessment and implementation plan report with the assistance of project participants, a technical committee, and stakeholder meetings. This project will be addressing the turbidity impairments within the Cottonwood River watershed. Project partners and participants have been established through the existing and ongoing Cottonwood River Restoration Project, which was sponsored by Clean Water Partnership program.     

The beneficial use of aquatic life is impaired for turbidity along three stretches of the Cottonwood River. Three tributaries of the Cottonwood River are also impaired for turbidity: Sleepy Eye Creek, Plum Creek, and two stretches of Dutch Charlie Creek.

The Total Maximum Daily Load (TMDL) assessment report will describe the magnitude of the problem from turbidity sources at the listed reaches. The TMDL implementation plan will provide direction for improving water quality and load reductions needed within the Cottonwood River watershed to meet water quality standards.

Listed reach name

AUID #

Listed pollutant

Impaired use

303(d) List scheduled start//Completion dates

Cottonwood River

07020008-501

turbidity

aquatic life

2004 // 2009

Cottonwood River

07020008-504

turbidity

aquatic life

2011 // 2015

Cottonwood River

07020008-508

turbidity

aquatic life

2011 // 2015

Sleepy Eye Creek

07020008-512

turbidity

aquatic life

2011 // 2015

Plum Creek

07020008-516

turbidity

aquatic life

2011 // 2015

Dutch Charlie Creek

07020008-517

turbidity

aquatic life

2011 // 2015

Dutch Charlie Creek

07020008-518

turbidity

aquatic life

2011 // 2015

Map and location

For more information, see TMDL Maps webpage and/or the Redwood-Cottonwood Rivers Control Area (RCRCA) website.

TMDL report and implementation plan

A preliminary draft TMDL assessment report and implementation plan are currently in development. It is anticipated that the draft TMDL assessment report and implementation plan will be completed by the fall of 2010.

Other documents

None.

Meetings and events

Specific information and meetings on the Cottonwood River Turbidity TMDL project is provided by the Redwood-Cottonwood Rivers Control Area (RCRCA) Web site.

Links

Information contact

Mark T. Hanson, Project Manager
Minnesota Pollution Control Agency
504 Fairgrounds Road, Suite 200
Marshall, MN 56258
507-537-7146