St. Louis River-U.S. Steel Superfund Site: Major Chronological and Future Events


Action/Report Date PCA Acceptance
Proposed Plan-Sediments* Spring 2009
Focused Feasibility Study-Sediments* Fall 2008

Five-Year Review*

April-September 2008

 

Sediment Investigation Remedial Investigation Report

February 2008

 

AMR 2006 February 2007 Pending

AMR 2005

February 27, 2006

Pending

Operable Unit Boundary Maps

Dece,ber 7, 2005

Pending

Chemicals of Interest in Sediments and Surface Water Report

August 31, 2005

November 13, 2007

MN Power installation of seven power line towers on site

July 11, 2005

Approved

Five-Year Review Recommendation Implementation Report

July 1, 2005

Pending

AMR 2004

February 10, 2005

 

Ecological Design Goals for (Sediment) Remedy (DNR)

January 10, 2005

 

Review of Sediment Data: Correlation between total PAH lab data and LIF data

November 3, 2004

Pending

Five-Year Review Sampling Event

November 2004

 

Data Audit and Review June 2004-October 2005

Sediment Characterization and Tier 1 Risk Assessment Report

April 13, 2004

November 13, 2007

AMR 2003

January 28, 2004

 

EPA Reuse Plan Session Meeting

December 15, 2003

 

Public Meeting- End of Five-Year Review

November 2003

 

First Five-Year review completion

September 23, 2003

 

Public Meeting

August 20, 2003

 

Sediment Characterization and Tier 1 Risk Assessment Work Plan, (subsequently QAPP, HSP)

May 22, 2003

Approved

Public Meeting for Start of Five-Year Review

May 15, 2003

 

AMR 2002

February 2003

 

LIF Investigation Report

July 24, 2002

Approved

Hydrogeologic Investigation Report

June 7, 2002

Rejected 12/17/2003

U.S. Steel Laser Induced Fluorescence supplement to the Sed. Characterization and Risk Assessment work plan

March 8, 2002

Approved 3/8/2002

LIF survey of river sediments

March 2002

 

AMR 2001

February 7, 2002

 

Public Meeting

February 7, 2002

 

Repair of OUJ Berm

August 2001

 

AMR 2000

June 20, 2001

 

Installation of piezometers near river

January 2001

 

U.S. Steel Hydrogeologic Investigation supplement to the Sed. Characterization and Risk Assessment work plan; Revision 2

November 30, 2000

Revised

Sediment Characterization and Risk Assessment work plan

September 29, 2000

Revised

U.S. Steel Focused Feasibility Study-sediments

June 1998

Rejected

Removed underground coke oven pipe lines

1999

 

OUJ and OUP remedy construction

1996-1997

 

Updated annually. Last Revised: February 2008
* = future actions